Collin courthouse filings list $90.3 million in estimated addition and garage work

AI-generated conceptual architectural scale model of a civic addition and garage; not an actual Collin County building, approved design or project rendering.
On this page

Collin County registered a $70.7 million estimated courthouse addition and a $19.6 million estimated parking garage with the state on November 19. The two projects are at the existing courthouse site, 2100 Bloomdale Road in McKinney. Their filed schedules begin in 2027; registration is not an announcement of a current entrance closure or a completed expansion.

Celina.news reported the new filings November 21. We checked both original Texas Department of Licensing and Regulation records and the separate county draft agenda referenced in that report.

The addition and garage have different timelines

The courthouse expansion filing, TABS2027006320, describes approximately 172,000 gross square feet and a connecting skybridge of about 4,530 gross square feet. It lists construction from March 8, 2027, through January 19, 2029, with a $70.7 million estimated cost.

The parking-garage filing, TABS2027006323, describes about 237,000 gross square feet. Its listed construction window is January 8, 2027, through January 8, 2028, with a $19.6 million estimate.

Both state records name Collin County as owner and PGAL as design firm. Both remain “Project Registered” at the November 21 check. The files classify them in the public-project funding category; they do not provide a complete financing plan or a household tax calculation.

The estimates add to $90.3 million, our calculation. That arithmetic should not be presented as a newly approved construction contract, final project budget or total cost including every related service. Under the filed forecasts, the garage finishes before the addition, but neither forecast guarantees a public opening date.

A December item is still a draft proposal

The county’s draft December 7 Commissioners Court agenda includes a proposal to deem Engineered Air Balance Co. the most qualified firm for commissioning services on the courthouse expansion and kitchen relocation, contract 2027-144, and authorize a professional-services agreement.

The agenda is explicitly marked draft. This is a proposed professional-services action, not a vote we have verified or a notice that the two state-filed construction projects are complete. Check the final county agenda and subsequent action record before treating that item as approved.

What matters for a trip to county court

Residents of the Collin County portions of the corridor may use the McKinney courts for hearings, jury service or records. These construction filings do not move a court date, change a summons or establish which entrance a visitor should use.

Before a visit, use the instructions from the court or office handling your matter. Confirm the building, check-in point and any current parking or accessibility notice. Do not substitute the proposed garage’s future availability for today’s parking instructions, or confuse the courthouse at 2100 Bloomdale Road with the administration building used for the commissioners’ meeting at 2300 Bloomdale Road.

Sources and review

Checked November 21, 2026: both TDLR registrations, the county’s draft agenda and the credited original report. Construction windows and costs remain estimates. No approved new tax rate, final construction award, opening date or current access restriction is claimed.