Anna puts Finley Park construction contract on the November 17 agenda

Conceptual illustration of blank meeting papers, a folder, calculator and pen on an empty meeting-room table in autumn
On this page

Anna has put the Finley Park construction agreement on the November 17 City Council agenda. The meeting is scheduled for 6 p.m. at the Anna Municipal Complex, 120 W. 7th Street. Council is being asked to consider a contract with Dean Construction and a guaranteed maximum price. The posted agenda establishes what is up for consideration. A vote, construction start and opening date still require separate confirmation.

What the council is being asked to decide

The posted November 17 City Council agenda) lists a resolution that would authorize the city manager to enter into a construction manager at risk agreement with Dean Construction, including a guaranteed maximum price for Finley Park.

Anna Weekly reported a proposed price of $6,656,100. The public agenda confirms the contract item and contractor but gives no dollar figure. The reported price remains attributed pending verification against an accessible contract attachment or the council record. The separate state project registration lists a $6.8 million estimated project cost. A filed estimate and a proposed contract price describe different things.

Where Finley Park is planned

The state project record locates the project at Finley Boulevard and Leonard Avenue. Anna’s parks project page describes it as a 28-acre neighborhood park formerly called Anna Crossing Park, with playgrounds, trails, a dog park, a pavilion, restrooms and parking in the plans. The state filing gives about 30 acres. Those planning records differ and neither sets a visitor-access boundary.

Which dates to use

The October engineering report gave October 27 as a staff target for presenting a contract. The November engineering report, on page 2, points to November 17 and lists fall 2026 for beginning construction and winter 2027 for completion. The February state registration gives June 1, 2026 and July 30, 2027 as its start and completion dates. The city parks page’s May update described a summer start and roughly a year of work.

Use the posted November agenda for the council meeting date. The construction schedules are forecasts from records prepared at different times. Wait for a city opening announcement before planning a visit or counting on reserving the pavilion.

Where to check after November 17

Use the Anna City Council page to check for agenda changes and for the meeting record after council considers the item. A later engineering report can show whether construction is underway. For places you can plan around now, see our Anna kids guide.

Reporting update

On November 14, 2026, we checked the posted council agenda and November engineering report and read Anna Weekly’s report on the proposed price. This update replaces the October 27 staff target with the date on the posted agenda. The story retains its original publication date.