Celina approves medical-office agreement: investment commitments and 2026–28 deadlines

Conceptual illustration of blank meeting papers, a folder, calculator and pen on an empty meeting-room table in autumn
On this page

Celina City Council voted 7–0 on October 13, 2026, to approve an economic development and performance agreement with Prime Healthcare Properties, LLC, for a proposed medical-office campus on Preston Road. The city's presentation describes two buildings, an estimated $18.35 million investment and a series of permit and construction deadlines extending into 2028.

The decision gives residents specific milestones to follow. It does not establish an opening date or currently available medical appointments. The vote and staff presentation appear near the beginning of the official October 13 meeting record, after the council returns from executive session.

Where the two-building campus is planned

Staff described almost 33,000 square feet of medical-office space on Preston Road, with shared parking and access behind the existing bank frontage. The presentation identifies the site between Lamar National Bank and SouthState Bank.

Community Impact's October 15 report by Jenna Stephenson places it south of FM 455 and reports that Texas Health Resources would occupy one building. That reporting helped surface the project; the council's own presentation supplies the commitments and vote discussed here.

The location description identifies a development site. A final visitor address, entrance and operating hours have not been established in the sources reviewed.

The investment forecast and minimum commitments differ

The $18.35 million figure is the estimated project investment, including tenant improvements. Staff also relayed a developer estimate of 64–80 jobs. Neither should be substituted for the lower minimum commitments described in the agreement presentation.

Staff identified $14.5 million in minimum capital investment and 42 minimum full-time-equivalent positions, describing commitments involving Prime and Texas Health Resources. The distinction matters when assessing later progress: an estimate describes the anticipated project, while the stated minimum describes the performance commitment presented to council.

These are project and employment figures, not patient charges or a promise that a particular specialty will be accepting appointments.

What city assistance was presented

The staff presentation described a roadway impact-fee credit of a little over $1.3 million, plus a $100,000 permit-fee grant. These are different forms of development assistance; the presentation does not describe the entire amount as an unrestricted cash payment.

This report relies on the public presentation for those rounded figures. We have not reviewed an executed agreement establishing the detailed disbursement conditions, repayment remedies or final amount of credits used. Approval of the agreement does not prove that every benefit has already been paid or claimed.

Three deadlines to follow through 2028

The city presentation specifies three developer milestones:

  • December 1, 2026: a building permit is required.
  • January 1, 2027: work on the property must commence.
  • December 1, 2028: a certificate of occupancy must be obtained.

Those are the requirements presented at the October 13 meeting. The review does not establish that the permit has been issued or construction has begun. Later permit and construction records would answer that separately.

The occupancy deadline is not a confirmed first day of patient care. Staffing, tenant readiness and an operator's service announcement still matter to someone deciding where to seek an appointment.

What residents should look for next

Staff listed targeted specialties including orthopedics, sports medicine, cardiovascular care, urology, oncology and gastroenterology. Treat these as the project's intended medical mix, rather than a verified roster of operating practices.

The next useful updates would be a permit milestone, a documented construction start and a dated operator announcement identifying actual services and opening arrangements. Insurance participation, patient eligibility and appointment prices remain unverified; they cannot be inferred from the council's economic-development vote.

Sources were checked October 21, 2026. This is a report on a development decision, with no site visit or clinical-service review claimed. For established family outings elsewhere in town, see our Celina kids guide.