Celina is changing the sequence of planned road work near Glen Crossing so a permanent connection can be built before repairs to Glendenning Parkway. The change follows residents' concerns about neighborhood access during construction, according to Community Impact's November 2 reporting.
The temporary connection was not the chosen approach
At the October 13 council meeting, the agenda included a $72,825 change order for a temporary Old Log Trail connection to County Road 53. The city's indexed meeting transcript records a motion to deny that change order and direct staff to change the scope to the permanent concrete option.
That distinction matters: the temporary-connection amount shown on the agenda is not the price of the more extensive approach council directed staff to pursue.
What the concrete option would do
The discussion describes concrete work on Old Log Trail and part of CR 53 before the Glendenning asphalt repairs. The purpose is to give the neighborhood another route during the later road work. The city discussion also references feedback from residents and nearby institutions about access.
Community Impact reports that the Old Log Trail connection would reach the Glen Crossing neighborhood, with the Glendenning work to follow. A proposed sequence does not establish today's detour, road closure or construction start. Residents should use current city notices for travel decisions.
Cost and timing remain planning figures
The council discussion puts the concrete work at approximately $3 million, followed by about $1.3 million for Glendenning repairs, for roughly $4.3 million combined as an estimate. The engineering discussion includes contingency and design considerations; this is not a final invoice or a newly verified construction contract total.
Community Impact reports a roughly 26-month design-and-construction sequence extending into late 2028 or early 2029. Those are reported planning projections, not guaranteed completion dates. Later design decisions, contracts and construction notices may change the timetable.
What Glen Crossing residents should watch next
Watch for the revised scope returning through the city's capital-project and contracting process, followed by a dated construction notice explaining access. An October council direction is different from a notice to start work.
Use the city's official website for new notices and the council recording for the October discussion. For other local family plans, see our Celina kids guide.
Community Impact's original local reporting and the city's indexed meeting transcript were checked November 6, 2026. Direct playback access to the council video was restricted during this check; no claim is made here about a current closure or a subsequent construction award.