Prosper approves The Marco zoning: what the 143-acre plan allows and what comes next

Owned conceptual illustration of moving boxes and house keys on a North Texas porch; not a photograph or rendering of The Marco.
On this page

Prosper Town Council approved zoning for The Marco on October 27, according to Community Impact's report of the vote. The decision allows a mixed-use plan on about 143 acres at the northeast corner of the Dallas North Tollway and U.S. 380. It is a zoning decision, not an announcement that the lagoon, homes, stores or hotels have opened.

What the council acted on

The town's October 27 agenda packet, item 13, identifies the request as ZONE-26-0009: amend part of Planned Development-42 and rezone a commercial tract to create a mixed-use planned development. The property is bounded by the tollway, U.S. 380 and the BNSF railway. Land across U.S. 380 to the south is in Frisco, but the zoning action is Prosper's.

Jenna Stephenson of Community Impact reported that the council approved the rezoning unanimously. The agenda packet, prepared before the meeting, shows that town staff recommended approval and that the Planning and Zoning Commission had recommended it 4–2 in August. The packet is not a post-meeting vote record; readers who need the adopted ordinance or a roll-call record should check the town's meeting archive as those records become available.

What the plan permits

The town's development standards in the packet cap housing at 4,400 units total: up to 2,500 mid-rise flats, 400 high-rise units, 500 age-restricted units, and 1,000 villas, townhomes, cottages, court homes or live-work units. The categories other than mid-rise flats can shift at the preliminary site-plan stage within the overall cap. Those figures are ceilings, not a construction schedule or a promise that all units will be built.

The concept places offices and hospitality along the tollway and highway, with a village core around a lagoon and canals. The staff report anticipates office space, a grocery or market hall, a performing-arts venue and up to two hotels. Selected buildings at the highway corner and inside the lagoon area could reach 14 stories or 190 feet; most of the remaining site is limited to eight stories or 160 feet. These are allowed limits in the plan, not confirmed building heights.

The project's representative described an estimated $2 billion private investment to Community Impact. That is the developer's estimate, not a town appropriation or a verified final cost. No public opening date is established in the records reviewed here.

What residents should watch next

The town packet says the conceptual layout still needs preliminary site-plan and site-plan review, including engineering and fire-code compliance. It specifically notes that fire access to the lagoon must be worked out. The packet outlines three phases, beginning with exterior areas, the lagoon and sitewide infrastructure; later portions depend on purchasers. That makes construction timing uncertain even after zoning approval.

For neighbors, the practical next documents are the adopted ordinance and exhibits, preliminary site plans, road-access and engineering reviews, and any announced construction timetable. Start with Prosper's meeting archive and planning department. Treat a rendering or marketing estimate as a concept until the relevant plan and permits are final. This account is based on the official packet and Community Impact's October 28 reporting, checked October 28, 2026.