Little Elm High School has a newly registered $53 million second-phase project covering an auto shop, fine-arts spaces and cafeteria work. The state filing gives a January 2027 start and August 2029 completion, but those are submitted project dates, not promises that particular rooms will open then.
What the new filing actually says
The Texas Department of Licensing and Regulation registered TABS2027003451 on October 13, 2026, for Little Elm High School at 1900 Walker Lane. It identifies Little Elm ISD as owner and PBK Architects as designer. Read the new state project record.
Its scope separates 28,920 square feet of additions from 104,810 square feet of renovations. The additions include CTE auto-shop and art space plus band and percussion halls. Renovations include cosmetology, kitchen and cafeteria work, repurposed athletics and rearranged fine-arts spaces. The registry’s scope text cuts off at its final item, so it does not establish a complete room-by-room program.
Two phases, two different sets of dates
An earlier state record describes a much larger package at the same campus. Keep these records separate when reading construction headlines, y’all.
State filing | Submitted dates | Estimate and size | Scope described |
|---|---|---|---|
TABS2027003451, registered October 13, 2026 | January 4, 2027–August 31, 2029 | $53 million; 28,920 square feet added and 104,810 renovated | CTE, fine arts, kitchen/cafeteria and repurposed spaces |
TABS2024022406, registered July 3, 2024 | January 2, 2025–July 1, 2027 | $110 million; 264,525 square feet listed | Classroom wings, a 2,500-seat arena, auxiliary gym and tennis courts |
The earlier description also includes a combined arena/gym tornado-shelter design. Its current registry status is Review Complete. That describes the record’s review status; it does not certify that construction is finished or students can occupy every space. Read the earlier project record.
What the $53 million does not establish
The figure is an estimated construction cost in a state accessibility-project filing. This record alone does not establish a newly approved bond, a tax-rate change, a final contract price or an occupancy authorization. Adding $53 million and $110 million together would not, by itself, produce a verified total approved campus budget.
The new record currently says Project Registered. Its submitted timeline also does not settle individual classroom moves, student schedules, parking restrictions or bus changes. Families should wait for district instructions on those operational details.
What families should check next
Save the new record number when comparing later updates. Useful next evidence would identify which phase and specific space an announcement concerns, whether its dates have changed and what students need to do. A general campus progress report should not be read as a campus reassignment notice.
For younger siblings and family outings away from campus construction, our Little Elm kids guide collects local options.
Reporting and source dates
LittleElm.city’s report led us to the second-phase filing. We read both state records on October 20, 2026. This report adds a phase-by-phase comparison and distinguishes registry milestones from student-use decisions; it does not claim a site visit or an independently verified construction start.