Aubrey council members are scheduled to consider up to $45,700 for engineering-report work on a proposed connection to Upper Trinity Regional Water District at their October 22, 2026, 6 p.m. meeting. Staff describes the work as preparation for anticipated surface-water delivery in 2028.
The item is a proposed amendment to Plummer Associates’ source-blending agreement. It does not establish that the connection is approved by state regulators, that construction is complete or that customers are receiving the new supply.
What is on Thursday’s agenda
Item 11 of the October 22 council agenda asks the council to act on Amendment No. 2 and authorize the city manager to execute the documents. The meeting is listed at Council Chambers, 226 Countryside Drive, Aubrey.
The supporting staff report recommends approval. That recommendation is not a recorded council vote. This preview was researched October 20; check the city’s latest agenda and subsequent action before treating the proposal as adopted.
What the $45,700 would cover
The supporting council packet, pages 592–596, describes a signed and sealed Interconnection Engineering Report for submission to the Texas Commission on Environmental Quality. The packet is a large download of about 284 MB.
The proposed work includes coordinating with the city and regional supplier, reviewing existing system and water-quality information, evaluating capacity and the anticipated blended water, and preparing the report. Deliverables include a draft, a final report and one round of responses to routine TCEQ comments.
The proposed amendment has a $45,700 fixed-fee ceiling. Staff identifies the 2026 surface-water-delivery bond as its funding source.
Read the contract figures in context
The amendment letter’s budget table shows how the proposed addition fits the broader source-blending contract:
Budget component in the packet | Listed amount |
|---|---|
Basic service | $98,595 |
Additional service | $50,000 |
Amendment No. 1, WSIG application support | $25,000 |
Proposed Amendment No. 2, interconnection support and report | $45,700 |
Total contract shown with the proposed amendment | $219,295 |
The $219,295 is the table’s broader contract total, not the price of this amendment alone or an individual household charge. The packet does not establish a new customer bill amount from this item.
What remains outside this scope
The letter excludes new field sampling or laboratory testing, hydraulic modeling and detailed construction plans and specifications. It relies on information supplied by the city and wholesale supplier. Further treatment design or additional studies could be additional services if the evaluation indicates they are needed.
Those limits matter: authorizing a report is one step in a proposed interconnection, not the same as completing every engineering, regulatory and construction requirement.
What it means for an Aubrey household
2028 is staff’s anticipated delivery year, not a guaranteed household switchover date. This source check did not establish an exact service-start date, construction timetable or final regulatory approval.
First check the water provider on your own bill. An Aubrey mailing address does not automatically establish service by the city system. Our Aubrey moving guide explains why address-specific provider checks matter; the separate rate-study proposal concerns how service costs might be reviewed, rather than this report’s technical scope.
Sources and the next decision
Aubrey.city’s October 20 report brought attention to this item. We checked the original agenda, complete packet and the relevant staff and amendment pages, including the compensation table, on October 20.
Follow the council’s action, then any executed amendment, regulatory review and dated city project updates. For a separate family outing, our Aubrey kids’ guide lists local options. The water proposal remains a council decision to follow, not a change to an outing or a current emergency notice.